Did you know that that six cameras are now trained on the developing East Village Green, allowing the public to track progress on the emerging 60,000-square-foot park in real time?
The future park will be located in an area bounded by 13th, F, 14th and G streets. It will encompass two separate areas for small and large unleashed dogs, a two-level community center, a children’s playground, a central lawn, a cafe, and underground parking that will accommodate 185 vehicles.
The four-acre project began moving ahead full steam in 2022 and is expected to be completed in mid-2025.
Live camera views can be seen at:
https://app.oxblue.com/?openlink=BarnhartReeseConstructionInc/EastVillageGreen
Email jgoodman@actionlife.com if you would like the link sent to you.